Facility Name:
|
Burlington North
|
Caller Name And Title:
|
Matthew Dow, Wastewater Facilities Manager
|
Municipality:
|
City of Burlington
|
Location (street or site):
|
Gazo Ave. CSO
|
Incident Start Date:
|
08/04/2020
|
Incident End Date:
|
08/04/2020
|
Incident Start End Times:
|
08:34 pm to 09:23 pm
|
Estimated Duration Of Event:
|
|
Nature Of Incident:
|
Authorized Wet Weather CSO Overflow
|
Estimated Volume (gallons):
|
6,637 gallons
|
Cause Of Discharge:
|
High Flows
|
Type Of Obstruction:
|
|
Point Of Discharge:
|
Combined sewer overflow structure
|
Corrective Action Taken:
|
none
|
Waterbody Impacted:
|
Intervale Wetlands
|
Contact Name And Title For Public:
|
Megan Moir, Div Head Water Resources
|
Call Date:
|
|
WW Staff Called:
|
|
Type Of Notification:
|
nForms
|
Public Overflow Report For Web:
|
Y
|
|
|
|
|
|
|
Description Of Incident:
|
High flows caused by an intense rain storm on 8/4/2020 resulted in the discharge of a combination of sewage and stormwater from Gazo Ave CSO. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
nForm Submission Number:
|
HP1-S6NC-HD0Q2
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|