Facility Name: Burlington Main    
Matthew Dow, Director of Wastewater Facilities    
City of Burlington    
Burlington Main Wastewater Treatment Facility    
07/28/2026    
07/28/2026    
04:28 pm to 05:30 pm    
   
Other    
857200    
Other    
   
WWTF outfall    
During the event, the disinfection dose was increased. The flow of treated combined sewer overflow stopped before staff were able to confirm that the increased dose was effective.    
Lake Champlain    
Matthew Dow, Director of Wastewater Facilities    
   
   
nForms    
Y    
   
   
   
This discharge was treated, partially disinfected combine sewer overflow that is treated and disinfected at the Main WWTF. Burlington Main plant had a CSO treatment event due to a large amount of rain in a short amount of time. During monitoring and testing of the event, a disinfectant test showed a need to increase disinfection. Staff made changes but were unable to confirm appropriate levels of disinfected before the flow from the CSO treatment stopped. Testing is in process. Those results will be available the evening of Wednesday, July 29th.    
   