Waste Water Inventory Website
            Watershed Management Website Drinking Water Website Waste Management Website
View FacilityIncident Record


Facility Name: Burlington Main    
Matthew Dow, Director of Wastewater Facilities    
City of Burlington    
Pine Street CSO    
10/08/2025    
10/08/2025    
12:05 am to 01:15 am    
   
Authorized Wet Weather CSO Overflow    
51221    
High Flows    
   
Combined sewer overflow structure    
none    
Pine Street Barge Canal    
Matthew Dow, Director of Wastewater Facilities    
   
   
nForms    
Y    
   
   
   
High flows caused by an intense rain storm on 10/8/2025 resulted in the discharge of a combination of sewage and stormwater from the Pine Street CSO. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.    
   
HQG-6E4J-0XYXE