Facility Name:
|
Burlington Main
|
|
|
Matthew Dow, Wastewater Facilities Manager
|
|
|
City of Burlington
|
|
|
Lake St
|
|
|
04/16/2023
|
|
|
04/16/2023
|
|
|
03:57 pm to 04:09 pm
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
Under 100 gallons
|
|
|
Obstruction/Blockage
|
|
|
Sewer blockage
|
|
|
Stormwater collection system
|
|
|
Staff limed the area and investigated the catch basins. It appears that a small amount of flow entered the catch basin, but that the sewage was unlikely to drain to Lake Champlain. Staff also jetted the collection system and vactored (using a vacuum truck to suck out all the water and debris)the catch basins attached to the storm system in the area. This posting is done out of an abundance of caution.
|
|
|
Lake Champlain near Burlington Boathouse
|
|
|
Matthew Dow, Wastewater Facilities Manager
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
Last night a sewer manhole on Lake street discharged untreated sewage to a storm system catch basin. The overflow was caught soon after it started.
|
|
|
|
|
|
HPS-ZBCZ-01B6J
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|