Waste Water Inventory Website
GoTo=>             Watershed Management Website Drinking Water Website Waste Management Website
View FacilityIncident Record

Skip Navigation Links

Facility Name: Burlington Main    
Caller Name And Title: Matthew Dow, Wastewater Facilities Manager    
Municipality: City of Burlington    
Location (street or site): Pine Street CSO    
Incident Start Date: 07/18/2021    
Incident End Date: 07/18/2021    
Incident Start End Times: 03:26 am to 07:50 am    
Estimated Duration Of Event:    
Nature Of Incident: Authorized Wet Weather CSO Overflow    
Estimated Volume (gallons): >100,000 to 500,000 gallons    
Cause Of Discharge: High Flows    
Type Of Obstruction:    
Point Of Discharge: Combined sewer overflow structure    
Corrective Action Taken: none    
Waterbody Impacted: Pine Street Barge Canal    
Contact Name And Title For Public: Megan Moir, Div. Head Water Resources    
Call Date:    
WW Staff Called:    
Type Of Notification: nForms    
Public Overflow Report For Web: Y    
   
   
   
Description Of Incident: High flows caused by an intense rain storm on July 18th, resulted in the discharge of a combination of sewage and stormwater from the Pine Street CSO. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings. The duration of time is stated longer than actual. There was a mechanical issue with the alarm which prevented the alarm from resetting when the CSO stopped discharging. The stop time is when staff reset the alarm. The flow has been approximated in the 100,000-500,000 gallons range. historical data shows the flow around 150,000 gallons or less.    
   
nForm Submission Number: HPA-9WPC-02RR9