Facility Name: Burlington Main    
Matthew Dow, Wastewaster Facilities Manager    
City of Burlington    
Burlington Main Plant    
08/11/2020    
08/11/2020    
08:06 pm to 08:19 pm    
   
Discharged treated and partly disinfected effluent    
1,000,000 to 1,500,000 gallons    
Chem Feed Problem    
   
WWTF outfall    
Operators on site attended to the issues and restarted the disinfection system. Furthermore, the city of Burlington residence have approved an upgrade to the disinfection system. This upgrade is under contract and will be started in the coming months.    
Lake Champlain    
Megan Moir, Div. Head Water Resources    
   
   
nForms    
Y    
   
   
   
Last night, 8.11.2020, during a massive thunderstorm Burlington Main plant switched over to emergency power during a power outage. During that time the CSO sodium hypochlorite disinfection pumps did not cycle on due to a fault caused by the electrical disruption. Two staff members were on site and immediately went to fix the problem. Within 13 minutes the pumps were activated and full disinfection commenced. We will continue to investigate why these pumps did not actuate correctly. The dry weather process was not affected by this failure.    
   
HP1-YQ71-VRKEA