Facility Name:
|
Burlington Main
|
|
|
Matthew Dow, Wastewater Facilities Manager
|
|
|
City of Burlington
|
|
|
Park Street CSO
|
|
|
08/02/2020
|
|
|
08/02/2020
|
|
|
11:17 pm to 11:49 am
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
Estimated at 20,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
Intervale Wet Lands
|
|
|
Megan Moir, Div. Head Water Resources
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 8/2/2020 resulted in the discharge of a combination of sewage and stormwater from Park St. CSO. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HP1-QQ7A-FHQZV
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|