View FacilityIncident Record


Facility Name: Burlington Main    
Matthew Dow, Wastewater Facilities Manager    
City of Burlington    
Park Street CSO    
06/30/2020    
06/30/2020    
05:12 pm to 05:35 pm    
   
Authorized Wet Weather CSO Overflow    
Estimated at 10,000-20,000 gal    
High Flows    
   
Combined sewer overflow structure    
None    
Intervale Wetlands    
Megan Moir, Div. Head Water Resources Dept.    
   
   
nForms    
Y    
   
   
   
High flows caused by an intense rain storm on 6/30/2020 resulted in the discharge of a combination of sewage and stormwater from the Park Street CSO. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.    
   