Facility Name:
|
Burlington Main
|
|
|
Matthew Dow, Wastewater Facilities
|
|
|
City of Burlington
|
|
|
Pump Station on Rockland St Burlington
|
|
|
11/01/2019
|
|
|
11/01/2019
|
|
|
12:15 am to 02:00 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>1,000 to 10,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Manhole
|
|
|
As intensity of the rain diminished, the pumps were able to handle all the flow entering the pump station.
|
|
|
Intervale Wetlands
|
|
|
Matthew Dow, Wastewater Facilities Manager
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
Due to extreme flows overnight from an intense rain storm. The Rockland St pump station was not able to handle all the excess flow from the rain storm. This cause some combination of rain water and sewage to overflow the pump station and run down into the Intervale Wetlands.
|
|
|
|
|
|