Facility Name: Burlington Main    
Matthew Dow    
City of Burlington    
Pine Street CSO    
06/18/2018    
06/18/2018    
03:11 pm to 03:44 pm    
   
Discharged untreated sewage    
25,000    
High Flows    
   
Combined sewer overflow structure    
In an effort to reduce overflows from the Pine St CSO, the City has disconnected some upstream catch basins from the sewer system and is developing a long term plan to eliminate this CSO.    
Pine Street Barge Canal    
Megan Moir, Div. Head Water Resources    
   
   
nForms    
Y    
   
   
   
High flows caused by an intense rain storm on 6/18/2018 resulted in the discharge of a combination of sewage and stormwater from the CSO located on Pine St. This CSO is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings. The sewage component is estimated to be approximately 1,200 gallons.    
   
HNE-NCP7-BVYDG