Facility Name: Burlington Main    
Matthew Dow, Wastewater Facilities Manager    
City of Burlington    
Pine St. CSO    
07/25/2018    
07/26/2018    
09:32 pm to 12:10 am    
   
Authorized Wet Weather CSO Overflow    
65,705    
High Flows    
   
Combined sewer overflow structure    
none    
Pine St Barge Canal    
Megan Moir,Div Head Water Resources    
   
   
nForms    
Y    
   
   
   
High flows caused by an intense rain storm on 7/25/2018 resulted in the discharge of a combination of sewage and stormwater from CSO . This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings. This CSO was intermittent : First start was 9:32 PM-9:51 PM, and again from 10:17 PM -12:10 AM.    
   