Facility Name:
|
Burlington Main
|
|
|
Matthew Dow, Wastewater Facilities Manager
|
|
|
City of Burlington
|
|
|
N. Champlain and Manhattan Dr
|
|
|
07/25/2018
|
|
|
07/25/2018
|
|
|
09:39 pm to 09:54 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
>1,000 to 10,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
none
|
|
|
Intervale Wetlands
|
|
|
Megan Moir, Div Head Water Resources
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 7/25/2018 resulted in the discharge of a combination of sewage and stormwater from CSO at N.Champlain and Manhattan Dr. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HNF-JZM6-Z8A77
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|