Facility Name: Burlington Main    
Matthew Dow, Wastewater Facility    
City of Burlington    
Burlington Main WWTF    
07/10/2018    
07/11/2018    
10:33 pm to 12:32 am    
   
Discharged treated and undisinfected effluent    
3,000,000    
Other    
   
WWTF outfall    
When operators arrived they found the PLC had failed. Operators started the appropriate pumps manual and monitored the disinfection from there. The event stopped around 12:30AM. An operator stayed through the night to monitor this system, and are currently working on the fix.    
Lake Champlain    
Megan Moir, Div Head Water Resources    
   
   
nForms    
Y    
   
   
   
A sudden rain storm increased the flows to Burlington Main plant. This activated the wet weather treatment system. The disinfection PLC failed, causing the disinfection pumps to no turn on. Operators attempted to start the system remotely before responding. Approximately 58 minutes of the event was not disinfected.    
   