Discharged untreated sewage
|
|
|
>10,000 to 100,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
In an effort to reduce overflows from the Pine Street CSO, the City has disconnected some upstream catch basins from the sewer system The City is developing a long term plan to eliminate this CSO.
|
|
|
Pine Street Barge Canal
|
|
|
Megan Moir, Water Resources Div. Head
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm and snow melt on January 12th resulted in the discharge if a combination of sewer and stormwater from the CSO located on Pine Street. This CSO is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|