Facility Name:
|
Burlington Main
|
|
|
Matthew Dow, Chief Operator
|
|
|
City of Burlington
|
|
|
Pine Street CSO
|
|
|
06/23/2017
|
|
|
06/23/2017
|
|
|
08:35 am to 09:43 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>10,000 to 100,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
In an effort to reduce overflows from Pine Street, the city has disconnected some upstream stormwater catch basins from the sewer system, and is developing a long term plan.
|
|
|
Pine Street Barge Canal
|
|
|
Megan Moir, Water Resources Div. Head
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm and snow melt on June 23rd resulted in the discharge of a combination of sewage and stormwater from the CSO located on Pine Street. This CSO is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and o prevent backups into homes and other buildings. We estimate the sewage component to be approximately 2,900 gallons.
|
|
|
|
|
|
HN5-T7VE-WN0FY
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|