Facility Name:
|
Burlington Main
|
|
|
Matt Dow - Chief operator
|
|
|
City of Burlington
|
|
|
Pine Street CSO
|
|
|
02/25/2017
|
|
|
02/26/2017
|
|
|
06:57 pm to 12:31 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>10,000 to 100,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
Some catch basins have been disconnected from this CSO. The City is developing a long term plan to eliminate this CSO.
|
|
|
Pine Street Barge Canal
|
|
|
Matt Dow
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm and snow melt on February 25th resulted in the discharge of a combination of sewage and stormwater from the CSO located on Pine Street. This CSO is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
2PM-FTHC-A1JX
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|