Facility Name:
|
Burlington Main
|
|
|
Tim Grover, Chief Operator
|
|
|
Burlington DPW
|
|
|
Pine Street Burlington VT
|
|
|
09/11/2016
|
|
|
09/11/2016
|
|
|
05:30 am to 05:56 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>1,000 to 10,000 gallons
|
|
|
High Flows
|
|
|
None
|
|
|
Combined sewer overflow structure
|
|
|
Some upstream catch basins have been disconnected from the combined sewer system. The City is developing a long term plan to eliminate the CSO.
|
|
|
Pine Street Barge Canal
|
|
|
Megan Moir, Water Resources Director
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 9/11/16 resulted in the discharge of a combination of sewage and stormwater from the CSO located on Pine Street.This CSO is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and buildings.
|
|
|
|
|
|