Facility Name:
|
Burlington Main
|
|
|
Tim Grover, Chief Operator
|
|
|
Burlington DPW
|
|
|
Park St Burlington
|
|
|
07/14/2016
|
|
|
07/14/2016
|
|
|
03:02 pm to 03:32 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
>100 to 1,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
Intervale Wetlands
|
|
|
Megan Moir - Assisstant Director of Public Works (water Resources)
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 7/14/16 resulted in the discharge of a combination of sewage and stormwater from CSO at Park St. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
2H2-EBCA-GBCY
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|