Facility Name: Burlington Main    
Tim Grover Chief Operator    
City of Burlington    
Pine Street CSO    
06/05/2016    
06/05/2016    
06:07 pm to 07:45 pm    
   
Discharged untreated sewage    
>1,000 to 10,000 gallons    
High Flows    
   
Combined sewer overflow structure    
In an effort to reduce overflows from the Pine Street CSO, the City has disconnected some upstream stormwater catch basins from the sewer system, and is developing a long term plan to mitigate CSO's from this location in the future.    
Pine Street Barge Canal    
Megan Moir Water Resources Director    
   
   
nForms    
Y    
   
   
   
High flows caused by an intense rain storm on June 5th resulted in the discharge of a combination of sewage and stormwater from the Pine Street CSO. This CSO is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.    
   