View FacilityIncident Record


Facility Name: Burlington Main    
Tim Grover Chief Operator    
City of Burlington    
Pine Street CSO    
02/24/2016    
02/25/2016    
11:21 pm to 03:37 am    
   
Discharged untreated sewage    
>10,000 to 100,000 gallons    
High Flows    
   
Combined sewer overflow structure    
In an effort to reduce overflows from the Pine Street CSO the City disconnected some upstream stormwater catch basins from the sewer system last fall and is developing a long term plan to eliminate this CSO    
Pine Street Barge Canal    
Laurie Adams    
   
   
nForms    
Y    
   
   
   
High flows caused by an intense rain storm on 2/24-2/25/16 resulted in the discharge of a combination of sewage and stormwater from the CSO located on Pine Street This discharge is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.    
   