Facility Name:
|
Bellows Falls
|
|
|
robert wheeler chief operator
|
|
|
Bellows Falls
|
|
|
80 mill street
|
|
|
12/01/2020
|
|
|
12/01/2020
|
|
|
02:00 am to 06:30 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>100,000 to 500,000 gallons
|
|
|
Other
|
|
|
breaker tripped in influent pumping buil
|
|
|
Stormwater collection system
|
|
|
we called the fire dept. to set up pumping, we were to get electricians to trouble shoot the problem and found tripped breakers and after resetting breakers the power was turned back on the influent pumps were up and running.
|
|
|
Connecticut River
|
|
|
Scott Pickup
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
The power that feeds the influent building and run the influent pumps were tripped out ,it is unknow why this happen. The rest of the plant had power.
|
|
|
|
|
|