Facility Name: Ludlow    
joseph gaudiana    
village of ludlow    
into the black river behind village pizza - ludlow, vermont    
07/10/2023    
08/01/2023    
10:00 am to 03:30 pm    
   
Discharged untreated sewage    
>1,000,000 gallons    
Crack/Hole in Pipe    
   
Other    
m&m excavating removed the old broken sewer pipe and replaced it with heavy duty "Blue Brute" piping. 300 feet of piping was replaced which was the entire length of pipe between two manholes.    
black river to connecticut river    
joseph gaudiana - chief operator    
   
   
nForms    
Y    
   
   
   
the july 10 flood in ludlow caused the river to rise over its banks and eroded the land next to the river exposing our 14-inch asbestos cement sewer main which carries 95% of the towns sewage to the wwtf. the river water then deposited many feet of gravel and rocks on top of the exposed sewer main puncturing the top of the pipe. the weight from the rocks and gravel eventually moved the pipe over enough to crack the pipe and break apart its joints in several places.    
   
HPX-2E1Q-CV6V6