Facility Name:
|
Barton
|
|
|
Jeremiah Borsoi Acting Chief Operator
|
|
|
Barton
|
|
|
Lagoon #1 and #2
|
|
|
12/18/2023
|
|
|
12/21/2023
|
|
|
02:00 pm to 02:30 am
|
|
|
|
|
|
Discharged partially treated disinfected effluent
|
|
|
>100,000 to 500,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
WWTF outfall
|
|
|
Increased flow through the plant, increased disinfection chemicals and blew out the feed pipe between lagoons to clear any obstruction impeding flow.
|
|
|
Barton River
|
|
|
Vera LaPorte Business Manager
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
2" of rain caused heavy flows to our plant. Lagoon #2 started overflowing at 1400 followed by lagoon #1 overflowing at 1545.
|
|
|
|
|
|
HQ0-02CG-4ZM16
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|