Facility Name: Barton    
Jeremiah Borsoi, acting chief operator.    
Barton Village    
From Lagoon #2 overflow pipe, disinfected through the plant and discharged into    
12/11/2023    
12/11/2023    
01:00 pm to 11:00 pm    
   
Discharged partially treated disinfected effluent    
>1,000 to 10,000 gallons    
High Flows    
   
WWTF outfall    
Increased flow through the wastewater plant to lower lagoon along with added sodium hypochlorite and sodium bisulfite for disinfection and increased epic for phosphorus removal.    
Barton River    
Jeremiah Borsoi    
   
   
nForms    
Y    
   
   
   
Melting snow, rain and added snow fall increased flow to our lagoon because of infiltration in our sewer system.    
   