Facility Name:
|
West Rutland
|
Caller Name And Title:
|
Seth Pietryka Superintendent
|
Municipality:
|
West Rutland
|
Location (street or site):
|
Wastewater Treatment Plant
|
Incident Start Date:
|
05/11/2025
|
Incident End Date:
|
05/13/2025
|
Incident Start End Times:
|
12:00 pm to 02:00 pm
|
Estimated Duration Of Event:
|
|
Nature Of Incident:
|
Discharged partially treated disinfected effluent
|
Estimated Volume (gallons):
|
2000000
|
Cause Of Discharge:
|
High Flows
|
Type Of Obstruction:
|
|
Point Of Discharge:
|
WWTF outfall
|
Corrective Action Taken:
|
Locking plant into storm mode. Maxing out UV's. Pulling manholes trying to find where all the infiltration is coming from.
|
Waterbody Impacted:
|
Clarendon River
|
Contact Name And Title For Public:
|
Seth Pietryka Superintendent
|
Call Date:
|
|
WW Staff Called:
|
|
Type Of Notification:
|
nForms
|
Public Overflow Report For Web:
|
Y
|
|
|
|
|
|
|
Description Of Incident:
|
Rain/ground water infiltration causing over 1MGD flows through the plant.
|
|
|
nForm Submission Number:
|
HQC-J393-CQ2R5
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|