Facility Name: West Rutland    
Caller Name And Title: Seth Pietryka Superintendent    
Municipality: West Rutland    
Location (street or site): Wastewater Treatment Plant    
Incident Start Date: 05/11/2025    
Incident End Date: 05/13/2025    
Incident Start End Times: 12:00 pm to 02:00 pm    
Estimated Duration Of Event:    
Nature Of Incident: Discharged partially treated disinfected effluent    
Estimated Volume (gallons): 2000000    
Cause Of Discharge: High Flows    
Type Of Obstruction:    
Point Of Discharge: WWTF outfall    
Corrective Action Taken: Locking plant into storm mode. Maxing out UV's. Pulling manholes trying to find where all the infiltration is coming from.    
Waterbody Impacted: Clarendon River    
Contact Name And Title For Public: Seth Pietryka Superintendent    
Call Date:    
WW Staff Called:    
Type Of Notification: nForms    
Public Overflow Report For Web: Y    
   
   
   
Description Of Incident: Rain/ground water infiltration causing over 1MGD flows through the plant.    
   
nForm Submission Number: HQC-J393-CQ2R5