Facility Name:
|
Barre City
|
|
|
Brandon Guyette
|
|
|
Barre City
|
|
|
Wastewater Treatment Plant
|
|
|
02/08/2024
|
|
|
02/09/2024
|
|
|
10:00 am to 08:00 pm
|
|
|
|
|
|
Other
|
|
|
>1,000,000 gallons
|
|
|
Chem Feed Problem
|
|
|
|
|
|
WWTF outfall
|
|
|
We had a chemical vendor come jar test, we found out are alkalinity is low and that is why its not settling well. We have added sodium bicarbonate to are oxidation ditch to raise the alkalinity. We are working toward switch back to sodium aluminate. On the ecoli retest on 2-10-24 we had a result of 2/100ml
|
|
|
Winooski River
|
|
|
Brian Baker Director of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
The wastewater treatment plant had a e-coli result of 1119.9 MPN/100 on 2/8/24. Clarifier #1 is not settling right and solids started floating over the weirs.
|
|
|
|
|
|
HQ1-9MXP-SSKTN
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|