Facility Name:
|
Barre City
|
|
|
William Ahearn
|
|
|
City of Barre
|
|
|
800 feet from Berlin- Barre City town line on US 302
|
|
|
10/31/2021
|
|
|
10/31/2021
|
|
|
02:00 pm to 07:00 pm
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>1,000 to 10,000 gallons
|
|
|
High Flows
|
|
|
none known
|
|
|
Manhole
|
|
|
Increased frequency of pump outs review and analysis of pumping schedule, staff instruction to assure timely return for a pump out. Further, engineering planning underway.
|
|
|
Stevens Branch
|
|
|
William Ahearn DPW Director
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows overtook standard pumping schedule. The combined wastewater overflowed the manhole, adjacent to the WACR Vermont Rail bed.
|
|
|
|
|
|