|
Facility Name:
|
St Johnsbury
|
|
|
Jim Brimblecombe - Chief Operator
|
|
|
St. Johnsbury
|
|
|
CSO – 10: (St. Mary’s Street behind Chaloux)
|
|
|
09/26/2024
|
|
|
09/26/2024
|
|
|
12:00 am to 12:20 am
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
6500
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
Passumpsic River
|
|
|
Steve Beauregard
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High Flows caused by heavy rain on 09/26/2024 resulted in the discharge of a combination of sewage and storm water from CSO - 10. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HQ6-Y35A-73EVE
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|