Facility Name:
|
St Johnsbury
|
|
|
Jim Brimblecombe - Chief Operator
|
|
|
St. Johnsbury
|
|
|
CSO – 10: (St. Mary’s Street behind Chaloux)
|
|
|
09/07/2024
|
|
|
09/07/2024
|
|
|
06:30 pm to 08:30 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
3449
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
Passumpsic River
|
|
|
Steve Beauregard
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High Flows caused by heavy rain on 09/07/2024 resulted in the discharge of a combination of sewage and storm water from CSO - 10. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HQ6-G1VK-6NQF3
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|