|
Facility Name:
|
St Johnsbury
|
|
|
Steve Beauregard, Director of Public Works
|
|
|
St Johnsbury
|
|
|
6, 6A, 7, 8, 9, 10, 14
|
|
|
07/13/2021
|
|
|
07/13/2021
|
|
|
05:00 am to 09:00 am
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
>1,000 to 10,000 gallons
|
|
|
High Flows
|
|
|
none
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
Passumpsic River
|
|
|
Steve Beauregard, Director of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on July 13, 2021 resulted in the discharge of a combination of sewage and stormwater from CSO 6, 6A, 7, 8, 9, 10, 14. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HPA-7S84-D64C1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|