Facility Name:
|
St Johnsbury
|
|
|
Chad Whitehead, Town Manager
|
|
|
St Johnsbury
|
|
|
cso006
|
|
|
01/12/2020
|
|
|
01/12/2020
|
|
|
06:00 am to 08:00 am
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
>1,000 to 10,000 gallons
|
|
|
High Flows
|
|
|
none
|
|
|
Combined sewer overflow structure
|
|
|
none
|
|
|
Passumpsic River
|
|
|
Chad Whitehead, Town Manager
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 1/12/2020 resulted in the discharge of a combination of sewage and stormwater from CSO 006. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HNW-S3QT-6224M
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|