Facility Name:
|
St Johnsbury
|
|
|
Hugh Wescott Public Works Director
|
|
|
St. Johnsbury
|
|
|
cso #016
|
|
|
06/11/2019
|
|
|
06/11/2019
|
|
|
04:00 am to 06:15 am
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
>1,000 to 10,000 gallons
|
|
|
High Flows
|
|
|
none
|
|
|
Combined sewer overflow structure
|
|
|
none
|
|
|
Passumpsic River
|
|
|
Hugh Wescott Public Works Director
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 6/11/2019 resulted in the discharge of a combination of sewage and stormwater from CSO #016. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|